Skip to content

Investors / Distributed battery energy storage

Investment opportunity

Distributed battery energy storage.

A 200-site behind-the-meter battery portfolio across UK commercial and industrial sites.

200

C&I battery sites over 5 years

105

sites live by month 24

£5m

initial, plus £15–25m call-down

c.2.3x

indicative base-case equity multiple

The opportunity

GridUnlock is building a portfolio of 200 battery energy storage systems on commercial and industrial sites over five years, with 100+ live inside 24 months. Instead of one large grid-scale battery waiting years for a connection, we install many smaller batteries behind the meter at sites that already have a grid connection, and earn from more than one revenue stream at each.

We are seeking £5m of initial investment, with a £15–25m call-down facility drawn site by site as the portfolio scales. In our base case the plan delivers around 200MW / 400MWh of storage, roughly £20m of annual revenue by Year 5, and an indicative 2.3x return on equity over a five-year hold.

The battery is the investment. EV charging, energy management and solar are added on the back of each battery, but the case does not depend on them.

The problem: grid-scale storage is stuck in the queue

  • Connection queues. NESO's December 2025 queue reform cut 153GW of battery projects from priority. Of the 83GW kept, only 33GW connects before 2030, and the rest up to 2035.1
  • Dates slipping for established players. One listed storage fund received 2029 energisation dates for two sites in April 2026 and warned its earnings target would slip as a result.2
  • Long development cycles. Land, planning, transmission assessment and a new connection mean years of spend before a single MWh is traded.
  • One revenue line. A standalone grid battery earns almost entirely from merchant trading, which investors discount heavily.

Our approach: many smaller batteries, behind the meter

  • Sites that already have a connection: quarries, transport depots and farms with existing grid capacity and large, steady energy use.
  • No cost to the host: the site gets cheaper, more secure energy and unlocked capacity without spending capital.
  • Managed as one portfolio: one reference design, one contract pack and one control platform, so site 150 is as repeatable as site 15.
  • GridUnlock aligned with investors: we earn as developer and operator and hold a growing stake in the portfolio.

Why it works

Grid-scale BESSGridUnlock distributed BESS
Time to revenueYears; connection dates into 2029–2035Months per site, using existing connections
PlanningFull planning, often contestedSmall footprint on existing industrial land
Development cost at riskHigh, front-loaded before connectionLow per site; capital drawn as each site is signed
Revenue streamsMainly merchant tradingContracted site energy services, plus grid trading and capacity income
Concentration riskOne site, one connection200 sites across sectors and regions
Add-on incomeNoneEV charging, energy management, solar

Revenue stack per site

  1. Contracted energy services to the host site (the bankable base)
  2. Wholesale and grid flexibility trading via a portfolio optimiser
  3. Capacity and balancing payments
  4. Add-on services: EV charging, energy management, solar

Rollout plan

Phase 1 · months 0–1230 sites across depots, quarries and farms, funded from the £5m initial investment. Proves the reference design and contract pack.
Phase 2 · months 12–2475 sites, with the call-down facility drawn as sites are signed.
Phase 3 · Years 3–5Steady build to 200 sites, with operating cash flow increasingly funding growth.

Cumulative sites in operation, base plan. Years 3–4 shown as an even build of 30–35 a year. Illustrative.

Indicative financials

In the base case, investor equity of around £17.6m at peak returns an indicative 2.3x over five years (c.30% IRR). Revenue reaches £20.1m and EBITDA £13.6m by Year 5.

ScenarioSite-level returnPeak equity drawnEquity multipleEquity IRR
Conservativec.8%c.£22mc.1.2xc.6%
Basec.11%c.£18mc.2.3xc.30%
Upsidec.13.5%c.£16mc.3.6xc.47%

Add-on services are upside, not base. EV charging, energy management and solar sold into the same sites add an estimated £2m a year of revenue by Year 5, and would lift the base multiple to around 3.7x.

How the capital works

  • £5m initial investment funds Year 1: development, the first 30 sites and the platform.
  • The £15–25m call-down is drawn only as sites are signed.
  • Portfolio debt of around 60% is introduced once sites are operating.
  • Total portfolio capex is around £100m.

Pre-NDA summary. Not an offer of securities. All figures are illustrative, built at portfolio level, BESS revenue only, and subject to verification with supplier pricing and live site data. Full assumptions are available under NDA.

Key risks and how we manage them

RiskMitigation
Site performance below planStrict site qualification on energy use and connection headroom; batteries sized to each site's real load
Trading price volatilityContracted site revenue as the base; merchant income discounted in the model; floor or tolling arrangement sought with the optimiser
Regulatory changeSites kept at or below 5MW; structure under review with specialist energy counsel
Hardware cost and deliveryPortfolio procurement across standard block sizes; tier-one equipment with performance warranties
Deployment paceCapital drawn site by site, so undeployed capital is never at risk; pipeline drawn from GridUnlock's existing fleet and industrial customers

Next steps

On signature of a mutual NDA, GridUnlock will share the full site and portfolio models, the commercial and contract structure, the first-phase site pipeline and the capital structure.

Sources: 1 NESO connections reform outcome, December 2025, as reported by Energy-Storage.news.2 Reported by The AIC, April 2026.

Book a site assessment